Construction Updates at Almonte, Country Terrace, and Village Green

As Omni Quality Living marks its 50th anniversary, our commitment to enhancing long-term care continues unabated. We are excited to share the latest construction progress updates at three of our residences, Almonte Country Haven, Country Terrace, and Village Green.

Almonte Country Haven

Almonte Country Haven is nearing the completion of several major projects, undergoing a transformative upgrade:

  • New Kitchen: The new kitchen, scheduled to open May 2025, is currently receiving its final touches with painting underway. This state-of-the-art space will significantly enhance meal service and dietary quality.
  • Multipurpose Spaces & Landscaping: Ongoing construction includes a multipurpose town hall, therapy room, brain gym, chapel, and offices. With landscaping begun in spring 2024, we anticipate a complete transformation by the end of June 2025.

For more information on Almonte Country Haven and to keep up to date with the latest construction updates, please visit: Almonte Country Haven – Omni Quality Living.

Country Terrace

At Country Terrace, we are in the final stages of an ambitious expansion:

  • Phase 2 Completion and Inspections: The second phase of Country Terrace’s expansion has been completed, with only the final inspection by the Ministry pending. This phase included significant renovations to enhance the home’s accessibility and aesthetic appeal.
  • Phase 3 Construction: Demolition of the East wing is scheduled to start in early Spring 2025, paving the way for the addition of eight new resident beds. Concurrently, the main entrance ramp has been demolished to improve accessibility as part of the ongoing construction efforts.

For more information on Country Terrace and to keep up to date with the latest construction updates, please visit: Country Terrace – Omni Quality Living.

Village Green

The new build at Village Green is shaping a legacy of care with its advanced construction stages:

  • Infrastructure Developments: The construction at Village Green is progressing smoothly, with commercial kitchen equipment installations underway in the basement level. On the first level, the focus is on completing ductwork, drywall, and suite flooring installations, ensuring each space meets Omni’s high standards for comfort and functionality.
  • Exterior Enhancements and Landscaping: The exterior of Village Green is taking shape with siding and cladding work ongoing. Landscaping activities are scheduled to begin in late Spring 2025, aimed at creating a welcoming and aesthetically pleasing environment for residents and visitors alike.

For more information on Village Green and to keep up to date with the latest construction updates, please visit: Village Green – Omni Quality Living.

The developments at Almonte Country Haven, Country Terrace, and Village Green highlight Omni Quality Living’s dedication to exceeding on the evolving needs of our residents. With these updates, we reaffirm our commitment to providing state-of-the-art homes that foster care, comfort, and community. As we move forward, these projects not only reflect our legacy of care but also our adaptive strategies to meet the future needs of our communities.

Stay tuned for ongoing updates and insights into our projects and their impact on our communities!